Top Products
RAPID (Refinery and Petrochemical Integrated Development) is Malaysia’s largest integrated oil and gas complex, located in Pengerang, Johor. The project includes an oil refinery, naphtha crackers, multiple petrochemical plants, an LNG import and regasification terminal, and a 1,600 MW utility plant equipped with four gas turbine generators and two steam turbine generators. Of this capacity, approximately 600 MW is exported to the national grid, while the remainder powers the RAPID complex. Its electrical distribution system ranges from 400 V up to 275 kV and comprises three 275 kV substations, twenty-two 33 kV substations, fifty-five 11 kV substations, and numerous low-voltage substations. More than 20 EPCC contractors were involved, each developing their own ETAP models, which PETRONAS needed to consolidate into a single integrated digital twin to validate overall protection and selectivity for the 275 kV system.
PETRONAS is Malaysia’s national oil and gas company, founded in 1974. Headquartered in Kuala Lumpur, it operates across the entire energy value chain - exploration, production, refining, petrochemicals - with a presence in over 100 countries.
Location: Kuala Lumpur, Malaysia
Year: 2021
Providing complex earthing protection coordination study for EPC contractors working for the RAPID project
Model integration at scale
Multi-vendor, multi-voltage system
Solidly grounded 275 kV system at both ends
Operating modes: radial vs ring
Grid constraints
Short-circuit contribution at the grid interconnection must be limited to 50%, requiring reactors at the tie point and careful protection coordination.
Need to go beyond traditional TCC curves
Which solutions did they choose?
To address these challenges, PETRONAS used ETAP as the common platform:
ETAP digital-twin modeling
PD Sequence-of-Operation (Star Sequencer)
Sequence network analysis
Construction of positive, negative and zero-sequence networks for SLG faults to understand zero-sequence paths and circulating currents.
Earthing & protection coordination studies
Key findings
1. Sympathetic earth-fault relay operation
Using PD Sequence-of-Operation, PETRONAS simulated a line-to-ground fault on one 275 kV transformer feeder:
If the main differential protection failed to clear the fault, these sympathetic operations could cause a wider outage of the complex.
2. Cause: double-ended solid grounding
Sequence network analysis showed that:
3. Limitations of directional 67N
Some consultants assumed that directional earth-fault protection (67N) would solve the issue. Simulations showed:
Why do they use ETAP?
Reliable integrated model
Uncovering of hidden protection issues
Clear, transmission-grade recommendations
From the study, PETRONAS issued corporate guidelines for 275 kV protection on RAPID and future projects (see below).
Improved system reliability & selectivity
By aligning practices with 132/275 kV transmission norms, the risk of widespread outages from a single SLG fault is significantly reduced.
Based on the ETAP study and industry best practice, PETRONAS recommended that RAPID and future projects adopt the following:
Install double main differential protection
275 kV transformer feeders should have two independent differential protections, as is common in transmission systems, to ensure fast and reliable fault clearing.
Use 67N only as backup
Directional earth-fault (67N) may be enabled only as backup to single-main protection, with pickup settings above the simulated circulating earth current and looking toward the transformer.
No stand-alone earth-fault O/C on 275 kV lines
What do they think about ETAP?
PD Sequence-of-Operation is a special feature that identifies the direction and magnitude of circulating earth current during line-to-ground faults, especially for circuits grounded at both ends. It helped us understand protection relay behaviour that is not visible on conventional TCC curves and to define solid recommendations for the RAPID project and future installations.By Mr. Rahman Waruah Matollah, Staff Engineer, Electrical Protection and Control, at PETRONAS
ETAP Digital Twin
eProtect
Grid Modeling & Visualization
Core Modules (Base Package)
Network Analysis
Transmission & Distribution Protection - StarZ™
System Grounding & Earthing
Star - Sequence-of-Operation