How Petronas conducted protection & selectivity studies for the RAPID project using ETAP Modeling

ETAP PD Sequence-of-Operation is a special feature that identifies the direction and magnitude of circulating earth current during line-to-ground faults, especially for circuits grounded at both ends. It helped us understand protection relay behaviour that is not visible on conventional TCC curves and to define solid recommendations for the RAPID project and future installations.
By Mr. Rahman Waruah Matollah, Staff Engineer, Electrical Protection and Control, at PETRONAS

RAPID (Refinery and Petrochemical Integrated Development) is Malaysia’s largest integrated oil and gas complex, located in Pengerang, Johor. The project includes an oil refinery, naphtha crackers, multiple petrochemical plants, an LNG import and regasification terminal, and a 1,600 MW utility plant equipped with four gas turbine generators and two steam turbine generators. Of this capacity, approximately 600 MW is exported to the national grid, while the remainder powers the RAPID complex. Its electrical distribution system ranges from 400 V up to 275 kV and comprises three 275 kV substations, twenty-two 33 kV substations, fifty-five 11 kV substations, and numerous low-voltage substations. More than 20 EPCC contractors were involved, each developing their own ETAP models, which PETRONAS needed to consolidate into a single integrated digital twin to validate overall protection and selectivity for the 275 kV system.


Providing complex earthing protection coordination study for EPC contractors working for the RAPID project

Challenges

Model integration at scale

  • Consolidate over 20 ETAP models from EPCC contractors into one coherent model of ~5000 buses.
  • Validate data consistency and ensure all models use the same network topology and settings.

Multi-vendor, multi-voltage system

  • Voltage levels from 400 V up to 275 kV, with mixed transmission and industrial practices.
  • Need one common model for short-circuit, transient stability, harmonic and reliability studies.

Solidly grounded 275 kV system at both ends

  • 275 kV transformers at sending and receiving ends are solidly grounded to optimise insulation cost.
  • This raises the question of circulating earth current and sympathetic relay operation during single-line-to-ground (SLG) faults.

Operating modes: radial vs ring

  • 275 kV system normally operates radially, but can form a ring (N+1) via interconnections between key substations.
  • In ring mode, earth-fault currents can be bidirectional, complicating 67N settings.

Grid constraints

  • Short-circuit contribution at the grid interconnection must be limited to 50%, requiring reactors at the tie point and careful protection coordination.

Need to go beyond traditional TCC curves

  • Conventional time-current characteristic (TCC) checks from EPCC contractors looked acceptable.
  • PETRONAS needed a more advanced technique to reveal hidden mis-operations.

Which solutions did they choose?

Selected applications

To address these challenges, PETRONAS used ETAP as the common platform:

ETAP digital-twin modeling

  • Integration of all EPCC models into a single, validated ETAP project representing the entire RAPID power system.
  • Single source of truth for short-circuit, load flow, transient stability, harmonics and reliability analyses.

PD Sequence-of-Operation (Star Sequencer)

  • Simulation of single-line-to-ground faults on 275 kV transformer feeders.
  • Step-by-step replay of relay operations to detect sympathetic tripping and coordination issues that are not visible on TCC curves.

Sequence network analysis

  • Construction of positive, negative and zero-sequence networks for SLG faults to understand zero-sequence paths and circulating currents.

Earthing & protection coordination studies

  • Evaluation of earth-fault current distribution in radial and ring configurations.
  • Assessment of existing EPCC protection settings (51N, 67N, differential, distance and overcurrent backup).


Key findings

1. Sympathetic earth-fault relay operation

Using PD Sequence-of-Operation, PETRONAS simulated a line-to-ground fault on one 275 kV transformer feeder:

  • Healthy 275 kV feeders experienced circulating earth-fault current greater than 1 p.u., reaching about 364 A against a line rating of 250 A.
  • Earth current flowed in both directions on some feeders in ring configuration.
  • As a result, 51N and 67N relays on healthy feeders picked up unnecessarily.

If the main differential protection failed to clear the fault, these sympathetic operations could cause a wider outage of the complex.

2. Cause: double-ended solid grounding

Sequence network analysis showed that:

  • Solidly grounded transformers at both ends provide a zero-sequence path through healthy feeders.
  • This allows circulating earth current to flow during SLG faults, even on feeders without faults.
  • At 33 kV, the same effect exists but is mitigated by neutral earthing resistors, so currents are smaller.

3. Limitations of directional 67N

Some consultants assumed that directional earth-fault protection (67N) would solve the issue. Simulations showed:

  • Because the system can operate radially or in a ring, earth-fault current direction is not fixed.
  • 67N alone cannot reliably discriminate sympathetic operation in all configurations.

Why do they use ETAP?

Main customer benefits

Reliable integrated model

  • PETRONAS obtained a single, high-fidelity ETAP model of the entire RAPID complex, validated across all EPCC designs.
  • Multiple engineering teams and even university collaborators can now run different types of studies on the same dataset.

Uncovering of hidden protection issues

  • PD Sequence-of-Operation revealed sympathetic relay behaviour that appeared acceptable in conventional TCC reviews.
  • PETRONAS could proactively address these issues before energising the system.

Clear, transmission-grade recommendations

  • From the study, PETRONAS issued corporate guidelines for 275 kV protection on RAPID and future projects (see below).

Improved system reliability & selectivity

  • By aligning practices with 132/275 kV transmission norms, the risk of widespread outages from a single SLG fault is significantly reduced.

 

PETRONAS Recommendations for 275 kV protection

Based on the ETAP study and industry best practice, PETRONAS recommended that RAPID and future projects adopt the following:

Install double main differential protection

  • 275 kV transformer feeders should have two independent differential protections, as is common in transmission systems, to ensure fast and reliable fault clearing.

Use 67N only as backup

  • Directional earth-fault (67N) may be enabled only as backup to single-main protection, with pickup settings above the simulated circulating earth current and looking toward the transformer.

No stand-alone earth-fault O/C on 275 kV lines

  • In line with typical practice at 132 kV and 275 kV, there is no requirement for separate earth-fault overcurrent protection on these solidly grounded lines.
    Rely instead on differential, distance and backup phase overcurrent schemes.

What do they think about ETAP?

Customer perspectives

PD Sequence-of-Operation is a special feature that identifies the direction and magnitude of circulating earth current during line-to-ground faults, especially for circuits grounded at both ends. It helped us understand protection relay behaviour that is not visible on conventional TCC curves and to define solid recommendations for the RAPID project and future installations.
By Mr. Rahman Waruah Matollah, Staff Engineer, Electrical Protection and Control, at PETRONAS

There are over 20 ETAP models from various EPCC contractors. A team led by my department was assigned to integrate all the models into one. We have to perform simulations of the complex as one integrated system. I can say that the integrated model reached up to 5000 buses if we look into the 275 kV system.
By Ir. Rahman Wanis Mustafa, Staff Engineer, Electrical Protection and Control, PETRONAS



Videos

Protection & Selectivity in Industrial Facilities

PETRONAS RAPID project is the largest oil & gas refinery and petrochemical plant in Malaysia which is powered by a 1200MW utilities plant and connected to a 275kV Grid supply. The integrated ETAP model for the RAPID complex reached up to 5000 buses that consist of various distribution voltages from 400V up to 275kV. Protection Coordination evaluation study for the RAPID complex was performed using “PD Sequence-of-Operation” to identify abnormal relay behavior, which may not be observed in the conventional TCC curve. When simulating earth fault at 275kV system, there is sympathetic relay operation at all 275kV healthy feeders due to circulating earth fault current. The circulating earth fault current is more than 1pu, which will potentially cause a broader outage to the RAPID complex. Further analysis has been performed by the author and academician experts to ascertain the root cause of the circulating earth fault current. This presentation will discuss the root cause of sympathetic relay operation during 275kV earth fault simulations and the recommended solutions to mitigate the sympathetic operation. This will help engineering design firms and plant operators clearly understand the protection relay behavior during faults by utilizing ETAP special features.


Solutions


Packages/Products