As part of a tailings-dam expansion project, a large, long-operating copper mine in southern Peru needed to increase its power capacity while maintaining continuous operation and high reliability. Existing demand at the tailings area was about 8 MW and had to be increased to 20 MW, including the installation of a new 30 MVA transformer. Operators were already observing excessive voltage drops, especially when large 4.16 kV, 1,250 hp motors started. A complete review of the electrical system was required. Electro Integra used ETAP to create a detailed digital twin with around 1,000 electrical nodes, covering the whole path from 138 kV transmission down to 13.8 kV distribution and finally the 4.16 kV and 480 V loads.
Southern Copper Corp, a subsidiary of Americas Mining Corp, is a mining company. Its major products include copper, zinc, molybdenum, and silver. SCC operates mining, smelting, and refining facilities in Peru and Mexico and conducts exploration activities in Argentina, Chile, and Ecuador. Southern Peruvian operations include the Cuajone and Toquepala.Electro Integra SAC (EISAC) provides consulting, design, development, and related services to the mining, hydrocarbon, and industrial electricity sectors. Since 2000, Electro Integra has partnered with OTI to bring ETAP software solutions to the Peruvian market. Electro Integra services all ETAP customers in Peru by providing local technical support and training.
Location: Toquepala, Tacna, Peru.
Year: 2022
Providing electrical system study for expanded cooper mine
Which solutions did they choose?
Electro Integra relied on several ETAP modules and tools:
Digital Twin Modeling
Load Flow Analysis
Short Circuit Analysis
Motor Starting Analysis
Protection & Coordination (ETAP Star)
Model Validation
Why do they use ETAP?
What do they think about ETAP?
Using ETAP we built a detailed digital twin of the entire system, validated it against field measurements, and then executed all required studies - load flow, short circuit, motor starting, and coordination. This would have been extremely time-consuming without ETAP.
By Gilberto Luy, Technical Manager, Electro Integra SAC
Design and commission of a green-site power system including protection coordination for the entire site and implementation of IEC61850 communications, inter-tripping, inter-locking and protection blocking schemes.