Harmonic Mitigation Project in Steel Plant

nov. 8, 2021, 18:21
Duration : 17:10
External URL : https://www.youtube.com/embed/d6YRFJjL558
This presentation aims to explain the necessary steps to comply with national grid code standards; an exemplary case of a steel manufacturing plant with intensive use of induction furnaces and a THD that exceeded the Grid Code's limits. This presentation highlights compliance, analysis, engineering (electrical power system studies), and equipment designed to comply with the technical criteria and mitigation. ETAP was used to size a filter to mitigate harmonics and improve the power factor for 34.5 kV transformers for grid code compliance. 

Categories :
  • Estudio de caso
Tags :
Harmonic Mitigation Project in Steel Plant